1991founded with 4 employees and 2 new CNC machines in rented premises at the village Mellingen
1994first trade-fair appearance at EUROMOLD
1996starting with continuous apprentice training
1997moving with 18 employees into new own buildings with 850 m² at the industrial zone U.N.O. next to Nohra
1999adjustment of an own design centre
2000extension of the administration building up to 650 m²
2000installation of two laser welders
2003increase of the high-speed machining capacity by Roeders RP800
2005extension of the shop floor up to 1.300 m² by an annexe
20063 new DMC rise our milling capacity
2007opting for 5-axis-machining by DMU 70 eVo
2008mounting of a new gundrilling machine ST 1000
2009advancement of our equipment for wire EDM by Mitsubishi FA 10S
2011installation of a new automated 5-axis high-speed cutting centre, linked with a new die-sinking-erosion machine by Ingersoll along with a CMM
2012addition to capacity at 5-axis milling by one new Hermle C40
2014enhancement at 5-axis milling by one new Hermle C32, one more apprenticeship training for 3 young men starts at our shop
2015 Installation of a new 3-axis milling center Quaser MV 204P. Fair participation Fakuma Friedrichshafen
2016 Expansion of our capacity with a start hole Madra BT 4050 and a surface grinding machine Ziersch ZT 612
2017 Commissioning of a new wire eroding system Mitsubishi MV 2004R and a Quaser MV204V 3-axis milling center